UI QUESTION 1
The company you advise wants to carry out the material availability check automatically in the production order at various points in time. Which of the following options would you recommend? (Choose two.)
A. Goods receipt for the product produced with the order
B. Creation of the production order
C. Confirmation of the operation that the materials being checked are assigned to
D. Release of the production order
E. Goods receipt for a missing part
Answer: BD
QUESTION 2
In production order processing, for which of the following objects can you enter a confirmation? (Choose three.)
A. Work Center
B. Individual Capacity
C. Order
D. Operation / Suboperation
E. Trigger Point
Answer: BCD
QUESTION 3
Which statements are true for ECC Long-Term Planning (LTP)? (Choose two.)
A. Reorder point planned materials can be included in long-term planning.
B. In case of external procurement, long-term planning creates purchase requisitions.
C. A planning scenario must be released to use it in long-term planning.
D. Long-term planning generally is operational planning of important components.
Answer: AC
QUESTION 4
Which of the following activities within the KANBAN procedure normally triggers subsequent stock posting of the goods receipt?
A. Set Container in transport
B. Set Container in process
C. Set Container empty
D. Set Container full
Answer: D
QUESTION 5
Which of the following elements do you have to prepare for costing of a production order to function without errors? (Choose three.)
A. Assign costing variants to order type.
B. Propose a standard text key in work center.
C. Assign a production scheduling profile to the material master (product).
D. Enter formulas for costing in the work center.
E. Use an operation control key with the indicator costing-relevant.
Answer: ADE
QUESTION 6
In which of the following objects can you activate backflushing of components if you want to use this functionality during order confirmation? (Choose three.)
A. Work Center
B. Production Scheduling Profile
C. Material Master (Finished Product)
D. Routing
E. Material Master (Component)
Answer: ADE
QUESTION 7
Which of the following master data do you need to provide for process manufacturing? (Choose three.)
A. Resources
B. Master recipe
C. Serial numbers
D. Product cost collector
E. Production versions
Answer: ABE
QUESTION 8
In your company planning strategies are used in the SAP-ECC demand management that is based on consumption. Which of the following statements about consumption is true? (Choose two.)
A. A consumption situation is dynamic and is always restructured with the planning run.
B. Consumption can also take place between order reservations and planned independent requirements, depending on the strategy.
C. Consumption always takes place on the material level between the planned independent requirements
and the planned orders.
D. The consumption parameters (consumption mode and consumption interval) can be set in the material
master or in the MRP group.
Answer: BD